FPSC (Federal Public Service Commission) · ASF

Work-rate Problems set-1

Work-Rate Problems  · Mathematics/General Ability

191 MCQs
Showing 1–20 of 191 MCQs Page 1 / 10
1
A can do a piece of work in 10 days, and B can do the same work in 15 days. In how many days can they complete the work if they work together?
2
If X can finish a job in 20 days and Y can finish the same job in 30 days, how long will they take to finish it together?
3
A and B working together can complete a work in 12 days. If A alone can complete it in 20 days, in how many days can B alone complete the work?
4
P and Q together can do a piece of work in 8 days. If P alone takes 12 days to do it, how many days will Q take to do it alone?
5
A can build a wall in 8 days, and B can build it in 12 days. Working together, how many days will it take them to build the wall?
6
A, B, and C can complete a piece of work in 10, 12, and 15 days respectively. If they work together, in how many days will the work be finished?
7
X, Y, and Z can independently finish a project in 20, 30, and 60 days respectively. How long will it take for them to finish the project if they all work together?
8
A and B together can do a work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days can they complete the work if they all work together?
9
A and B can do a work in 8 days, B and C in 12 days, and A, B, and C together in 6 days. How long would A and C take to complete the work together?
10
A can do a piece of work in 24 days, B in 6 days, and C in 12 days. Working together, they will complete the same work in:
11
A can do a piece of work in 10 days and B in 15 days. They work together for 2 days, and then A leaves. How many days will B take to finish the remaining work?
12
X can do a job in 20 days and Y in 30 days. They work together for 4 days, after which X leaves. In how many days will Y finish the remaining work?
13
A and B can do a work in 12 and 15 days respectively. They began the work together, but B left 3 days before the completion of the work. In how many days was the total work completed?
14
A can finish a work in 10 days and B in 15 days. They start together, but A leaves 5 days before the completion of the work. How many days did the work take to complete?
15
A, B, and C can do a piece of work in 10, 12, and 15 days respectively. They started the work together, but A left after 2 days. In how many days will B and C finish the remaining work?
16
P can do a task in 15 days and Q in 20 days. They work together for 4 days and then Q leaves. P finishes the remaining work. How many days in total did P work?
17
A can do a work in 30 days and B in 45 days. They work together, but B leaves 5 days before the work is finished. What is the total number of days taken to finish the work?
18
A takes twice as much time as B to finish a piece of work. If they can finish the work together in 14 days, how many days will A alone take to finish it?
19
A is thrice as fast as B. If they finish a job together in 15 days, how many days will B alone take to finish the job?
20
A is 50% more efficient than B. If A can do a work in 20 days, how many days will B take to do the same work?